The Road is in - Boy that has been an ordeal. But it's done for now. September 2015 |
Zac had previously buried the pipe for the ditch, and then got it all leveled out. |
Digging post holes - The post hole digger that Ace Hardware rents was a piece of junk, and we didn't want to wait, so the digging commenced - September 2015 |
Everyone helped ! |
Zac had cemented the corner posts, and then ran a string line so the post holes would be in a good straight line. |
Beautiful pic - just as the sun was setting. Everyday after work, we would work until dark. |
Then the cementing of the poles began. We started everything on the South side, then across the back, and finally up the North side. |
These bags of dry cement (SAKRETE) each weighed either 50 or 80 pounds. I helped lay them out next to each hole, and I think that day I figured I had moved close to a ton ! |
They would dump the dry bag of cement in the hole, even it up, and then pour in a bucket of water. |
.........and by hand (and back) |
Zac was finishing up cementing the North side on this day. |
Landon was moving pipe. |
I think this was the first pipe that they set on top, and then decided that each of the posts would have to be notched. |
Zac did each of these by hand, after building a JIG that he would pop on and off each pole. Long tedious work ! - but Zac just got to it. It had to be done, right? |
Setting the top pole AFTER the notches has been made - much better. All of the top rail was welded in place............... I think these were each 24 feet long, which spanned 3 - 8 foot openings. |
Then the middle rails (8 feet each) were welded. Notice Tagg and Zac have the helmets, and Dad and Rog were looking away so there eyes wouldn't get burned. |
Zac had to build another JIG for this, to help hold the pipes, and also for measuring accuracy. |
Everyone pitched in and was a big help. One of the guys who Zac works with loaned Zac the big welder, and it was much appreciated. |
We were happy the days were still so mild. Most of this went on in October, and into November. |
After all of the welding was done, then the forming of the bottom wall was started. This was about mid-November. Still no snow, thank goodness. |
The first pour didn't go as far down the South side as was planned for. |
The second pour finished up the South side, went all along the back, and a little ways up the North side. |
Ernie Durrant and Steve Wiggill did the pouring, and Dad and Zac helped. |
And unfortunately the snow did not hold off, and the pour that had been scheduled had to be postponed. |
It was a great day in the snow, and the kids played and worked, and played and worked. |
No comments:
Post a Comment