Wednesday, January 1, 1986

1986 - Building our "House on the Hill"


February 1986
We went and looked at Stan and Sue Rees' house tonight.  They have hot water heat running through tubes in the floor, and we were thinking of doing the same thing.  Theirs is powered by a boiler and solar panels.  Our plan is to have ours be powered by a water jacket in a wood -burning stove.  Saturday we are going to a Solar place in Salt Lake City.  We are getting our bids together now for our new house.   It has been beautiful weather just like April, and it's only February.  It will be a real bummer to go back to winter.  We took a water sample from our well down to Weber Basin for testing today.  We'll know the results tomorrow.  We are getting all our bids collected and it looks as though we will borrow $50,000, plus put down $8,000 of dad's money.  We still need excavating, appliances, cabinets, carpets, linoleum, heating and cement work bids.  All of these together can't go over $17,000.  I took off work yesterday for a few hours and we went to Precision Built Homes, Artistic Woodcrafting (for cabinets), Interstate Brick and Pioneer Door.  Hope we can get everything squared away in another month and apply for the loan.

March 8
Looked at some more brick at Interpace.  We like "Homestead", this house is costing more and more.  I'll be glad when we finally get going on it.  I'm looked at carpet today at R.B.J. in Henefer, the bid was $2,800.  We have almost got all our bids now.  I can hardly wait till I write in my journal that the house is finished!! 

March 11
We found out that Precision Built Homes went out of business yesterday,  so we'll have to find someone to stick build our house.  Rog is down talking to Gary Randall now. He worked for Precision, and we heard that he was going to continue to stick build homes from Precision's plans.

March 18
We should be getting our tests back from Ford Chemical Lab very soon (water tests), then we go for the loan.  Things are hectic, but we'll make it. 

March 27
We checked on loans yesterday.  We will probably borrow $57,000 at 11% interest from The First National Bank of Morgan.  Our payments will be approximately $688.00 for 20 years.  But we will hopefully only use $50,000 or $51,000.  If we borrow $50,000 at 11% interest, the payments will be $579.00 per month for 20 years. That's not too bad.  I hope interest rates go down some more.  We need to decide whether to lock in now or take a construction loan and close out later.  Morgan Bank will work with us really good.  The Ogden banks require so much, such as 100% finished construction on the house and $2,000-$3,000 closing costs.  I know Morgan will work with us better.  I hope everything goes okay.  It's scary.  Maybe by this time next month we will be started.  Hope so. 

April 1986
It's been too long since I've written.  We've started on the house.  Broke ground for our house on the 7th, and the hole was dug April 8th, and then we got the footings in about the 11th.  Then it sat for a week of bad weather.  The foundation finally got done the 21st,  and the rough plumbing, and backfill of foundation on the 23rd, and now we are leveling the basement dirt to lay the coils down and pour the basement floor, hopefully by the 28th or 29th, because Gary Randall is framing it the 30th of April.  It is sure hectic.

April 29, 198
Well, it rained all last week and we won't be able to get the basement poured before the house gets framed.  Neil Boyce back filled the front and sides today and also fixed the road a bit, and the culvert.  Hope this nice weather stays. 

May 1986
The house was delivered today (the 2nd) in parts, and on the 3rd they started framing.  On the 5th the roof went on.  The 6th the interior walls done.

May 4th - It snowed 4  inches (we had to shovel it off the sub-floor)

May 6, 1986
The house is up.  Gary Randall and his crew finished framing it today.  It is all framed.  It looks great.  It's bigger than I thought.  Tar paper is on the roof, and Rog has got plastic on the windows.  The exterior doors are in also.  The weather is still a mess and it looks as though the basement floor will have to be put off another week.  Bret Kimball is getting the windows tomorrow, and we will probably put them in this weekend.  It is exciting, finally getting a house. 

May 7th  rough plumbing
May 8th electrical

May 9, 1986
Well, the house is all plumbed and the electrical work is being done now by Lynn Mickelsen and Roger. 

May 10th put windows in
May 14th poured basement floor
May 15th started shingles
May 17th finished shingles, put stairs in, windows done
May 19th laid coils on top floor
May 21st poured top floor, delivered brick
May 24th start working on storage tank for heating system
May 28th  finished electrical

May 29, 1986
The house will start being bricked today.  Also, insulation has to go in because the sheetrock has to be up and finished this weekend because the tapers are coming Monday.  The electrical is also done. 

May 31st sheetrocking done, chimney started

June 1986

June 2, 1986
The house is all sheetrocked and the tapers will start today.  Rog says it will take about 4 days.  Dean Judkins is working on the brick, and he will do the chimney first.  We need to get primer and paint so we can start this next weekend. 

June 3, 1986
Dean Judkins got the chimney all cinder blocked and the sheetrock tapers started taping last night.  They will finish Saturday morning.  So I guess the painting will wait for next Monday.  I will go and get paint this Saturday. 

June 7th buy paint, visit Fieldcrest cabinets
June 10th start painting

June 13, 1986
Well, we've started painting the house.  What a job!  Hope to get it all primed this weekend, then it needs 2 coats of paint!  Got the paint last Saturday.  It cost $231.00.  Got porcelain color (off white).  Susan, Layne’s wife came up and spent one whole day helping us paint.  She really helped out allot.  We really appreciated it.

June 14th paint
June 16th ordered cabinets
June 17th – 21st paint
June 28th bricking finished

July 1986

July 2nd pick out tile & stain for the wood trim
July 4th started to stain doors and stain and varnish all wood trims
July 8th finished shingling
July 15th tile started, heating system installed
July 16th cabinets and tile finished
July 20th  staining and varnishing is finally finished


August 1, 1986
We are so busy with the house.  Both Roger's and my heads are spinning.  The carpet and linoleum are finished and the fridge and stove are delivered.  We are getting the water line hooked up today, and then UP&L is supposed to be hooking us up and Mt. Bell (phone) should be in 10 days.  The plumber and electrician should come today to finish up.             

August 6th
There is electricity in the house now, and Dwight Gailey is supposed to hook up the finish plumbing today.  It will be good to have water in the house so I can start cleaning and then we can move in next week hopefully.  It seems you wait so long for some things to happen, and you think they never will, and then they FINALLY do. 

August 15, 1986
Well, we finally did it.  We are all moved into our new house.  I never thought this day would come.  But it has, and I'm glad and our house is so pretty and nice. 



No comments:

Related Posts Plugin for WordPress, Blogger...